Skip to content

Strategic & Tactical Plan — IU Alumni Platform (ALUMAP)

Period: Feb 4 – Jul 28 (≈ 24 weeks, 4 roadmap phases)

plan roadmap


Part 1 — Strategic Plan

1.1 Vision (where we want to be on July 28)

A self-hostable, university-operated alumni platform that can be handed over to a successor team and run for years with minimal intervention. By the end of July:

  1. The platform runs on university infrastructure.
  2. Every production change is gated by automated tests — not by exploratory testing.
  3. The system is observable enough that an on-call engineer can answer "is something broken?" in under 60 seconds from a single dashboard.
  4. The codebase is healthy enough that a new contributor can ship a feature in their first week without a senior pairing on every step.
  5. Every quality claim in our documentation is backed by an evidence artifact that anyone can re-run.
  6. New functionality (social and engagement features) is built on top of this foundation.

1.2 The strategic bet

ALUMAP is already in production. That changes the engineering problem. We are not building a system; we are evolving a running one through a server migration, feature phase, and 2 stabilization phases, without breaking the alumni already using it.

This forces three strategic choices:

  1. Stability > velocity in the migration phase, velocity > polish in the feature phases, polish > everything in stabilization. The order matters; the ratio shifts at each phase boundary.
  2. Quality investments are front-loaded. The test, security, and observability foundation built in phases 1–2 is what makes phases 3–4 fast. Feature work without that foundation looks fast for two sprints and then collapses.
  3. The migration is the forcing function for everything we should already have done. If we cannot restore from backup, we cannot migrate. If we cannot run the test suite headlessly, we cannot validate the migration. If our dashboards do not tell us when the platform is broken, we will not know if the migration broke it. We use phase 1 to fix all three.

1.3 Strategic objectives & success criteria

Each strategic objective has a measurable end-state checked at the end of project.

ObjectiveEnd-state criterion (Jul 25)Measured by
O1. Operational independencePlatform runs on university infrastructure; complete handover runbook exists; quarterly restore drill executedRunbooks committed in iu-alumni-infra/docs/; drill report dated within 90 days; deploy executed by a non-author
O2. Quality netBackend coverage ≥ 80% on critical modules; mobile ≥ 60%; frontend ≥ 50%; full E2E regression suite of ≥ 25 scenarios green on every releaseCoverage badges on every README; CI dashboards
O3. Security postureZero high-severity Bandit/Trivy/pip-audit findings; OWASP ZAP nightly green; quarterly threat-model review filedCI artifacts + ADR record
O4. Performance under loadAPI p95 ≤ 500 ms at 500 concurrent users (k6 evidence); map renders 1,000 markers in ≤ 3 s on a mid-range Androidk6 reports + Flutter DevTools timeline
O5. ObservabilityRED metrics for every service, USE metrics for every resource, alert routing for every P0/P1 condition, error budget dashboardGrafana dashboards as listed in QP §6
O6. Documentation completenessEvery public API endpoint documented; requirements traceability matrix 100% mapped; onboarding guide enables a new contributor to ship in week 1docs CI green; matrix coverage report
O7. Process maturityDORA: deployment frequency ≥ 1/day on main; lead time ≤ 24 h; change failure rate ≤ 15%; MTTR for P1 ≤ 1 hDORA dashboard + incident log
O8. Accessibility & usabilitySUS ≥ 75; WCAG 2.1 AA with 0 critical issues; ≥ 85% task completion in usability testUsability report + axe-core artifact

1.4 Strategic risks (top of mind, reviewed monthly)

RiskWhy it threatens the visionStrategic mitigation
Migration failure mid-windowCould destroy alumni trust and force a rollback to external server we no longer controlmigration is done on several stages and we have a backup plan of last stable stage to roll back to in state of emergency
Single-person (DevOps)One engineer holds the deploy, monitoring, and infra knowledgedocumentation of everything is done to ease catch up later, and we have contact with that person
Notification spam in engagement featuresMisconfigured notifications damage user trust faster than features build itinclude rate limits, opt-out, and an observability panel for notifications-per-user-per-day before the feature ships
Documentation rotDocs stop matching code, new contributors can't onboard, knowledge concentrates furtherdocs CI runs link/spell/lint and an OpenAPI-vs-doc diff on every PR; doc owner is named (Roukaya)

Part 2 — Tactical Plan (Phase-by-Phase)

Each phase has the same structure: theme → entry conditions → goals → workstreams → exit criteria → key risks → handoff to next phase. Exit criteria are the contract: a phase is not over when the calendar says so; it is over when the criteria are met. If it slips, it eats the next phase's buffer (deliberately reserved).

A standing rule applies in every phase: no production deploy goes out without all required CI checks green, and a rollback path documented. This is not repeated below; it is non-negotiable.


Phase 1 + 2 — Infrastructure Migration & Stabilization

Main objective

Move the platform from external hosting to university infrastructure. Lay down the foundation for easier future migrations if needed and environment for development.

Why this phase comes first

Every later phase assumes we can deploy reliably, observe production, and recover from failure. Any feature work done before that foundation lands is built on sand.

Entry conditions

  • The previous team has handed over the codebase, documentation, and access to the current hosting environment.

Goals

  1. Migrate all production services (API, mobile web, admin portal, Telegram bot, Postgres, Nginx, Prometheus/Grafana) to university infrastructure with ≤ 1 h cumulative downtime and zero data loss.
  2. Ratify the disaster-recovery procedure by performing one full restore drill from off-host backups before the migration date.
  3. Stand up the foundational quality CI:
    • Container scanning (Trivy) on every image build
    • Secret scanning (gitleaks) on every PR
    • Branch protection on every repo (required reviews, CODEOWNERS, required status checks)
    • Dependabot/Renovate enabled across all repos (currently only iu-alumni-infra)
  4. Rebuild Grafana dashboards around RED (per service) and USE (per resource) methods, retiring the cargo-culted PostgreSQL exporter panels.
  5. Define and publish the SLOs that the rest of the year will be measured against (availability ≥ 99.5%, p95 ≤ 500 ms, error rate ≤ 0.5%).

Workstreams

WorkstreamOwnerDeliverables
Migration executionDevOps leadMigration runbook (timed, scripted, dry-rehearsed twice); off-host backup verified; DNS cutover plan; rollback plan to old host valid for 14 days post-migration
CI hardeningDevOps leadTrivy + gitleaks added to every repo's workflow; branch protection rules applied; Dependabot manifests for backend/mobile/frontend
Observability rebuildDevOps leadRED dashboards per service; USE dashboards per resource; alerts set
Backup & DRDevOps leadOff-host daily backup target configured; restore drill executed and report committed; cron exit code scraped by Prometheus; alert if last-success > 26 h
Documentation foundationDocumentation leadOperational runbooks structure committed in iu-alumni/docs/

Tactical constraints

  • No feature work merges to main during the migration window (24 h before through 24 h after the cutover). Feature branches stay open; PRs can be opened but not merged.
  • The old host is not decommissioned for 14 days after migration; rollback path is held open for two weeks of soak time.
  • Migration is executed during low-usage hours (validated against Prometheus traffic data from the previous month).

Exit criteria

A phase-1 exit review checks each of the following. All must be green before phase 2 starts:

#CriterionEvidence
1Production runs on university infrastructure for ≥ 7 consecutive days with availability ≥ 99.5%Grafana SLI panel screenshot + uptime log
2Off-host daily backup is verified working and alerted on failurePrometheus alert history; sample restore from off-host backup
3RED + USE dashboards exist and replace the legacy PostgreSQL exporter viewGrafana dashboard JSON committed in repo
4Trivy + gitleaks fail builds on high severity in all four code reposCI run history showing intentional failure on a probe commit
5Branch protection enforces required reviews + status checks on every repoRepo settings screenshot

Phase 3 — Profile & Auth Stabilization (June 2 – June 30)

Main objective

Stabilize the user-facing experience by delivering the profile redesign with achievement badges, resolving outstanding authentication issues, and expanding test coverage while incorporating revised client priorities agreed in Sprint 12.

The follow feature is a lower priority for the client; Telegram-based event notifications remain on the roadmap but move to Phase 4. The phase end date shifted from June 23 to June 30 to align with the rescheduled mid-semester presentation.


Entry conditions

  • All core features working.
  • Platform and code stability are fully green.
  • Profile redesign requirements and badge definitions are approved by the client.

Goals

  1. Deliver the profile redesign: updated layout, graduation labels, and user achievement badges.
  2. Resolve authentication issues (email verification reliability, account recovery, alumni-approval separation from email verification).
  3. Introduce the Alumni / Alumni Friend registration roles with admin-panel verification flow.
  4. Expand test coverage for better reliability:
    • Backend: ≥ 75% overall, ≥ 85% on auth and profile modules
    • Mobile: ≥ 55% overall
    • Frontend: ≥ 50% overall
  5. Maintain release velocity:
    • Deployment frequency ≥ 1 deploy/day
    • Change failure rate ≤ 15%
  6. Push documentation maturity in parallel to avoid end-of-project compression.

Exit criteria

#CriterionEvidence
1Profile redesign shipped and verified on mobile web and nativeUAT sign-off + screenshots
2User badges visible on profiles and awarded correctlyIntegration test outputs
3All high priority auth bugs closedBug board
4Alumni-approval flow separated from email verificationIntegration test outputs
5Coverage targets achieved (backend ≥ 75%, mobile ≥ 55%, frontend ≥ 50%)Coverage reports
6DORA metrics maintained (≥ 1 deploy/day, ≤ 15% CFR)DORA dashboard
7OpenAPI vs documentation match ≥ 90%Docs CI report
8Zero open P0/P1 defectsProject board

Phase 4 — New Features & Final Stabilization (July 1 – July 28)

Entry conditions

  • Phase 3 exit criteria all green.
  • Projects Tab requirements finalized and approved by client.
  • Social feature scope confirmed (Telegram-based event notifications, follow feature if capacity allows).
  • Coverage and DORA metrics are at end-of-phase-3 levels.

Goals

  1. Ship the Projects Tab: a new section separate from Events where staff/admins can publish university projects with descriptions and donation links.
  2. Ship Social Features (in priority order):
    • Telegram-based event notifications (notify users about event updates and new events via the bot)
    • Follow feature (if capacity allows after Projects Tab and notifications are stable)
  3. Hit final coverage targets:
    • Backend: ≥ 80% overall, ≥ 90% on auth, ≥ 85% on events/profile/admin
    • Mobile: ≥ 60% overall, ≥ 75% on application/
    • Frontend: ≥ 50% overall, ≥ 65% on stores
  4. Run the full evidence-collection battery for every QAS in the Quality Plan:
    • Performance: k6 report at thresholds
    • Security: ZAP full scan + Bandit + Trivy + pip-audit reports clean
    • Accessibility: axe-core + Flutter scanner reports against WCAG 2.1 AA
    • Usability: SUS ≥ 75; task completion ≥ 85%
    • Reliability: 30-day uptime ≥ 99.5%; one quarterly restore drill
  5. Complete the documentation set:
    • Contributor onboarding
    • Requirements traceability matrix (100% mapped)
    • Architecture Decision Records for every major choice
  6. Validate handover by having a non-author execute a deploy from documentation alone.
  7. Prepare the defense exhibit set mapped to the strategic objectives.

Tactical constraints

  • No new features merge in this phase. Bug fixes only. The cutoff is the phase-4 entry meeting.

Exit criteria

#CriterionEvidence
1Projects Tab shipped: staff can create projects with donation links; users can view themUAT sign-off
2Telegram-based event notifications working: users notified on event updates/new eventsIntegration test outputs
3Alumni / Alumni Friend roles functional in registration and admin panelTest report
4Final coverage targets hitCoverage reports per repo
5All QASs have a current, committed evidence artifactTraceability matrix complete
6k6 load test green at QAS201 - QAS203 thresholdsk6 report
7Follow feature or similar if specified in detailsTest Report
8Usability: SUS ≥ 75, task completion ≥ 85%Study report
9Architecture Decision Records committed for every major choiceADR directory
10All P0/P1/P2 bugs closed; P3+ documented in handoverBug board

Key risks for this phase

  • Polish work expands to fill the schedule. Mitigation: weekly reviews with explicit "stop" criteria for each part.
  • Last-minute scope additions ("just one more feature"). Mitigation: scope freeze is calendared at phase entry; exceptions require PO approval and must trade against another item.

Final handoff

A 60-minute handover review:

  • Walk the strategic objectives; attach evidence to each.
  • Identify any criterion not met and the impact.
  • File the project closeout document; thank the team.